Remaining Work in Project Management – Definition and Meaning

The term “remaining work” in project management typically refers to the remaining effort or remaining duration needed to complete a task, work package, or the entire project. It is used in progress tracking and project control to quantify the unfinished portion of the work and to enable accurate forecasting of completion.

Example, best practice, and further information

If a task was originally estimated at 20 hours and 10 hours have already been worked, the remaining effort might still be 10 hours, or it may be updated to 15 hours if the task turns out to be more complex than expected. A best practice is to regularly reassess and update the remaining effort or duration by the responsible team members. This is a key input for progress measurement as defined in the PMBOK Guide and forms the basis for agile tools like burndown charts. It helps realistically assess project status and forecast the completion date.

Related Terms