Links in Project Management – Definition and Meaning

In project management, a link (also referred to as a dependency) defines the logical relationship between individual project activities and determines their sequence. Links are used to structure and control the project flow. They are typically visualized in network diagrams or schedules and specify the type of dependency, such as finish-to-start (FS) or start-to-finish (SF).

Example, Best Practice, and Further Information

In a manufacturing project, for example, a link may define that assembly cannot start until all required components have been delivered (a finish-to-start relationship). A proven best practice is to document links clearly and review their validity regularly throughout the project. This is in line with activity sequencing in the PMBOK Guide and agile dependency management practices. Well-defined and maintained links ensure a smooth project flow and help minimize bottlenecks.